Over the last two months:
- ADA compliance and 100 year flood plain issues addressed and compliance model accepted by four dozen attorneys validating their existence
- Course design approved by MUD Board
- Project plan including pavillion, tees/signs/baskets, 3 new wells which will give us constant level water holes, ADA compliant paths approved and sent out to bid
- Contractor assigned last week

The installation of the course begins August 18. Course ready for play (pavillion, tee boxes, baskets) in the October timeframe and completed (signs, benches, trash cans, tree removal/planting, two or three smaller pavillions, paths) another month or two after that.

Course fully open for tournaments and full time play in the November/December timeframe.