Re: walking the course
We were able to get out there yesterday and look at the upcoming work. For starters we won't need the rebar, TImmy will be donating all we need from his jobsite. The screen on the other hand we have to get our hands on. We're going to need 200 linear feet of 4 ft. wide screen.
The ball is in Goblins court and he will be leading all work crews, he can't post but can read the board, so please let him know on the board when you are available, he will be contacting you.
The decision has been made to pour all 19 boxes the same day. That date will most likely be the 28th of April. So all forms will have to be laid down in 4 weeks. We will have the concrete truck the entire day. Timmy will be working on getting a bobcat donated for the holes the truck can't drive to.
So the first action item is to go to the park next wed-thurs and mark the first 6 boxes so the city knows where to scrape. It is very likely that nobody will be needed Friday the 30th, but starting the next week is where the members will play there part at setting forms. We will put down 6 forms a week. Goblin will be building forms at his house the whole time. So let him know when you are available to go there and help him. I will keep putting info on the board for all volunteers by Goblins direction.
__________________
Gone but never forgotten, Ricky Wright.
What have you done for Disc Golf today besides play?
|